You must be using a Javascript-enabled browser to use this feature. Please enable Javascript or upgrade your browser.

Underground Cable Replacement

Underground Cable Replacement

Projects in Progress

Camelot Village Apartments Project Map90th & Blondo St | Camelot Village Apartments

Project Start Date: June 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Center Park Project Map156th & Spring St | Center Park

Project Start Date: June 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Meadowview map99th & Blondo St | Meadowview

Project Start Date: May 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Greenfields Project map163rd & Grover St | Armbrust Acres 1

Project Start Date: May 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Greenfields Project map156th & West Dodge Rd | Greenfields

Project Start Date: May 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Fountain Hills Project map156th & Pacific St | Fountain Hills

Project Start Date: May 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Armbrust Acres project map168th & Oak St | Armbrust Acres 3

Project Start Date: April 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Crosskey Village project map112th & Ohio St | Crosskey Village

Project Start Date: April 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Stonybrook South project map142nd & Chandler Rd | Stonybrook South

Project Start Date: April 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Golden Hills map36th & Hwy 370 | Golden Hills

Project Start Date: February 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Cedardale Rd. & Gold Coast Rd. | Gold Coast Apartments

Project Start Date: February 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

156th & Q St. | Chimney Ridge

Project Start Date: December 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

168th & Pine St. | Pacific Heights

Project Start Date: November 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

110th & Harrison St. | Brookhaven

Project Start Date: August 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

138th & Harrison St. | Holling Heights 

Project Start Date: August 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

150th & Dodge St. | Pepperwood Seville

Project Start Date: August 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

93rd & Blondo St. | Woodstone Townhouses

Project Start Date: June 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

132th & Blondo St. | Willow Wood

Project Start Date: May 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

33rd & Bedford Ave. | Adams Park Community Center

Project Start Date: May 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

163rd & Grover St. | Armburst Acres

Project Start Date: July 2021
Project Completion Date: February 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

90th & Harrison St. | Woodbine

Project Start Date: October 2021
Project Completion Date: February 2022

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

156th & West Dodge Rd. | Greenfields

Project Start Date: July 2021
Project Completion Date: December 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

132nd & Maple Rd. | Maple View Estates

Project Start Date: April 2021 
Project Completion Date: December 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

36th & HWY 370 | Bella West

Project Start Date: May 2021
Project Completion Date: November 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

108th & Fort St. | Escalante Hills 

Project Start Date: June 2021
Project Completion Date: November 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

96th & Lincoln St. | Overland Hills

Project Start Date: July 2021
Project Completion Date: November 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

168th & Pacific St. | Rose Garden Estates

Project Start Date: June 2021
Project Completion Date: November 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Antler Country area map204th (HWY 31) & West Maple Rd. | Antler Country

Project Start Date: June 2021
Project Completion Date: November 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

120th & Leavenworth Rd. | Wedgewood Condos

Project Start Date: April 2021
Project Completion Date: November 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

144th & Blondo St. | Autumn Heights

Project Start Date: April 2021
Project Completion Date: October 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

56th & La Platte Rd. | Riverview Forest

Project Start Date: July 2021
Project Completion Date: October 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

120th & Blondo St. | Willow Wood-Park West

Project Start Date: March 2021
Project Completion Date: October 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

222nd & F St. | The Farm

Project Start Date: May 2021
Project Completion Date: October 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

25th & Lynnwood Dr. | Stonecroft

Project Start Date: April 2021
Project Completion Date: September 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

84th & Giles Rd. | Tara Hills

Project Start Date: April 2021
Project Completion Date: September 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays. 

Washington St. & Schram Rd. | Glenwood Hills

Project Start Date: March 2021
Project Completion Date: September 2021

To keep your service reliable, OPPD has contracted with Nielsen Construction Co. and Central States Contactors Inc. to replace underground services and equipment in your neighborhood. Project work may last up to 3 months, barring weather or other unavoidable delays.